BC Hydro's 2026 Call for Demand made available only about 400 MW of new capacity for data centres (roughly 100 MW conventional plus 300 MW for AI) over two years from February 1, 2026, with a 145 MW ceiling per project and successful applicants notified around September 2026. Demand far exceeds that pool.
If your AI campus did not win an allocation, needs more than 145 MW, or cannot wait years in BC Hydro's interconnection queue, a grid connection is no longer the only way to energize it. GRECO builds behind-the-meter power — on-site generation plus grid-scale storage and liquid cooling — so the campus energizes on your timeline.
An energy-first campus still meets what BC rewards: environmental impact through ~97% heat recovery and district-heat export, community benefit and First Nations partnership, and Canadian data sovereignty and jobs.